After ceramic tile laying in home decoration, how to check and accept, how to see the laying master’s skill is good, how not to leave hidden dangers for the future life.
1. Pay attention to whether the floor tiles need to be parquet or paved in the same direction.
2. Check the flatness of the floor tile with a 2 meter level, the error shall not exceed 0.5mm, the height difference of the adjacent brick shall not exceed 0.5mm, and the flatness of the gap shall be 3 mm. When the floor tile is laid, other types of work shall not be polluted, and no human trampling shall be allowed. After the completion of the floor tile 24 hours to clean, with cleaning, and do maintenance.
3, the floor tile empty drum phenomenon is controlled within 3%, the empty drum on the main channel must be reworked, 3% single refers to a single corner empty drum, the whole block shall not be empty drum.
4. After the floor tile is paved, check whether there is any error, hollow, color difference, etc., use thick cardboard or splint and old carpet to cover all the protection, and the gap between the board must be tightly pasted with wide paper tape to prevent sundry entry.
5, under normal circumstances, the levelness of the floor tile is allowed to have 2 mm error, the gap of the floor tile must be consistent, brick and brick diagonal should be flat (allowed 0.3 mm error), kitchen, wall tiles in addition to brick and brick diagonal should be flat, but also water flatness (allowed 1 mm error) and perpendicality (allowed 2 mm error) to achieve, toilet, balcony floor tiles need to consider the floor drain, It is necessary to put good slope first, if there is no special reason there should be no water.
6. After the wall brick and floor brick are paved, it is necessary to use “sealant” or “white cement” for wet slurry caulking.
7, the brick surface gap is regular and consistent, the joint is uniform and neat, the brick seam is not more than 1mm, the porcelain error is not more than 0. 8cm.
8. Bathroom, balcony and kitchen floor tile with floor drain have enough self-drainage slope.
9. Whether the brick surface is broken or not.
10, tile direction is correct, there is no reversal phenomenon.
11, tile and waist line position is correct, no deviation or height error phenomenon.
After ceramic tile laying, the relevant information on the matters needing attention will be introduced here. I hope this article will be helpful to you. If you have what you don’t understand can continue to pay attention to the latest relevant information on our Fuwo home network, you can also leave a message to us below for consultation, we will answer for you as soon as possible.