In order to make the toilet waterproof effect better, before doing the toilet waterproof must first ensure that the toilet ground dry and clean, in addition to the toilet waterproof coating should also be good coated, there can be no omissions, bubbles, cracks and other conditions, otherwise it will not conducive to the back of the construction, so, toilet decoration waterproof how to do?

Toilet is our whole home use water most of a space, water is easy to the ground, but also easy to cause water, if the toilet waterproof do not do, it will lead to very serious water seepage, water leakage, not only to their own life caused a more serious impact, but also to the downstairs residents, not timely or inappropriate solution will cause discord in the neighborhood.

Steps of toilet floor waterproof practice

First, we should observe the water and electricity road of the toilet and transform it according to the actual situation, so as to have a detailed understanding of the hidden works. After a good scheme is determined, the water and electricity heating pipeline is laid and chiseled. Secondly, at the basic level of treatment, before the toilet waterproof engineering should be cleaned up its original decorative materials, and then the surface of the water slurry will be paved, and then waterproof treatment.

The second step, when doing the waterproof layer, should pay attention to whether the waterproof coating coating is uniform, the thickness of the waterproof layer should be more than 1.5mm, pay attention to the dead Angle, joint waterproof treatment. After the completion of construction should also be carried out 24 hours of water shield test: all the toilet sewer blocked, in the door to build a 25cm height of the wall, and then inject 20cm height of water, after 24 hours, observe whether there is leakage phenomenon, if there should be timely repair.

The third step, in the water test 5-7 days after the waterproof coating has formed waterproof film, should also be in the waterproof coating layer to do a layer of cement mortar protective layer. Doing so can effectively protect the waterproof coating, two convenient tile, at the same time can play a good leakage waterproof pressure pipeline. The last step is the laying of the wall and floor tiles.

It is necessary to do a good job of wall waterproof work before laying wall tiles. In general waterproof treatment, the wall needs to do 30cm high waterproof measures. If it is a non-load-bearing light body wall, it needs to do waterproof treatment for the whole wall, at least 60cm high.

Waterproof coating should be in accordance with the requirements of national and local regulations, qualified products. For the toilet waterproof coating work, in the wall and the ground joint is very key, must be the wall and the ground edge and corner, waterproof coating in place.

When laying waterproof floor tile, the original floor tile chisel away, we must first use cement mortar to smooth the ground, and then waterproof treatment, so as to avoid uneven smear, and the leakage of waterproof coating. Make sure the floor is also cleaned before waterproofing.

The groove of the water pipe should also be waterproof. During the construction process, the waterproof layer around the hole must be carefully constructed when the pipeline and the floor drain pass through the floor. The wall buried water pipe, to achieve a reasonable layout, laying water pipes are greater than the diameter of the groove, the groove plastered smooth, and then the groove brush waterproof paint.

Make sure the bathroom floor is smooth. If you need to replace the toilet floor tile, after the original floor tile chisel, you must first use cement mortar to level the ground, and then do waterproof treatment. This can avoid waterproof coating due to uneven thickness and leakage.

Toilet seams should be painted in place. The joint between the toilet wall and the ground, as well as the joint between the upper and lower water pipes and the ground, is the most prone to problems.

Wall treatment is also very important. In the general toilet waterproof treatment, the wall should also do about 30 cm high waterproof coating, to prevent water Yin permeating the wall. But if it is the wall of the bathroom is non-load-bearing light body wall, it is necessary to cover the whole wall with waterproof coating.