Carpentry renovation | Homeowners should do at least these five things during the same period

Carpentry renovation | Homeowners should do at least these five things during the same period

2023-02-28 04:02:46

Carpentry construction process, the owner should be prepared for the next phase of construction, there are at least four things to do at this stage. If the construction process is in accordance with my recommendations, it is the “water, electricity, wood, tile and oil” process, not the “water, electricity, tile, wood and oil” process, the progress of the site at this time should be the construction of water and electricity pipeline has been laid, the line groove has not been sealed, carpentry is The ceiling work is being carried out.

So, at this time, the owner should do what work?

A, notify the tile manufacturer delivery

Carpentry construction process, you need to notify the tile manufacturer delivery, the specific delivery time, you need to confirm with the workers, which is ready for the next stage of tiling.

Of course, all my tips are in advance, there have been a lot of spray said I so early why, put your home ah, I do not want to talk to these people whose heads were kicked by donkeys, I want to tell the owners are: first, advance notice manufacturers delivery time, is delivery time! And not instead of today to send over; second, you really do not worry about the tiles sent to the wrong home? The odds are still there, if sent to the wrong, and then replaced, at least 1-2 days delay, in addition, you really do not worry about the manufacturer’s inventory problems out of stock? I tell you, I have been in the business for 10 years, I have experienced these situations.

In addition, it should be reminded that the vast majority of tile manufacturers of workers regardless of moving tiles upstairs, you have to let the foreman arrange more workers to help you move tiles, the cost of moving tiles is best negotiated first, a box of tiles dozens of pounds only about 1 square meters, a lot of work.

After the arrival of tiles, the owners of friends must be a little check to see if the color is the original color they ordered, and then count the number of tile manufacturers in the contract will generally specify the return, replenishment period, generally ranging from 30 days to 60 days, the time different brands, you need to ask in advance.

Second, custom closet manufacturers initial measurement

Customized closet measurement is generally two times, a preliminary measurement, a remeasurement.

Initial measurement is generally in the renovation company into the construction site after a week or so, this time the demolition is over, the horizontal line should have, the purpose is to clarify the installation position of the closet or closet, manufacturers also have to communicate with the construction team plaster line, skirting and other issues. After the initial measurement, the closet designer can come up with a draft design first, and the owner can have a full communication with the closet designer, decoration designer and family members on the draft design.

The remeasurement can be arranged in the ground after the cement leveling, that is, the total height of the ground has been determined, you can ask the manufacturer door to door for remeasurement.

Third, the wooden door manufacturers initial measurement

Wooden door measurement is generally two times, a preliminary measurement, a re-measurement.

Initial measurement is generally in the renovation team after about a week, this time the end of the demolition, the horizontal line should have, the initial measurement of the site within the diameter of the doorway size, see if the doorway has a flat wall need to do door stack, see if the doorway is vertical in a line, if not vertical flat then need to level the foreman, these jobs need to communicate with the construction team on site.

The second measurement is in the kitchen and bathroom after the wall tile posting, if the ground needs leveling is in the ground leveling after, and can determine the height of the ground size, this time the doorway and the wall thickness of the size is the final size, you can remeasure; if there is a doorway transformation, it is necessary to notify the remeasure after the doorway transformation.

Fourth, the appointment of concealed works acceptance

After the plumbing and electrical piping is finished, the keel part of the ceiling of the carpentry has been built, and the decoration is carried out to this stage, you can make an appointment with the designer, supervisor and the team to carry out the concealed works acceptance.

Concealed works acceptance is a very important node of the entire home renovation process, I strongly recommend that the owners of friends must be on site and according to the acceptance specifications for strict acceptance, no sloppy, such as time is not well coordinated, rather than postpone the construction period for a few days, but also to take seriously, not to use video and photos instead of acceptance.

What is concealed works? Simply put, it is the construction project that will be hidden after the future decoration, and the surface can no longer be seen, mainly including: water supply and drainage works, electrical piping works, ceiling base, etc. The acceptance node of this stage is that the plumbing and electrical line slot has not been sealed, the ceiling or partition wall made by the carpentry project has not been covered with gypsum board.

This node acceptance is very important, if you find that there are problems with the water or electrical circuit, you can immediately rectify, and the cost of rectification will be very low; if you find that the light steel keel installation of carpentry is not standardized, you can also immediately rectify, and the cost of rectification is not high.

There has been a misconception in the industry: that the concealed works acceptance is plumbing acceptance. In fact, this is not professional people called, to be precise, concealed works acceptance should also include the concealed works acceptance of carpentry, as well as the next construction step to cover off all construction details. Write here, I think serious thinking friends, should understand that I strongly recommend that as far as possible carpentry before tiling into the field, right?

Five, stone ordering

Stone is mainly used in the window countertops, over the door stone, decorative walls, steps, bathroom countertops, etc., if the family does not have these items, can be ignored, however, no over the door stone is too little, right? This time to consider buying stone. Stone is also a product that needs to be processed, different sellers may process the cycle is different.